A project consists of 5 activities, A, B, C, D and E B, C can’t start until A has finished, D can’t start until C has finished, abd E can’t start until B and D have finished. The duration of A is 5, B is 8, C is 10, D is 19 and E is 15 How many days can activity B be delayed, without delaying the whole project, assuming the “Day 1” method?
Correct
Incorrect
Question 2 of 2
2. Question
A CPIF (cost-plus-incentive-fee) contract has an estimated cost to the seller of $165,000, and an Incentive fee of $13,500 has been negotiated. By the end of the contract, the seller’s actual costs are $147,350. What is the seller’s profit if the share ratio is 70/30?